Hi experts,
how can i issue the material to outside the company.
The scenario is that we have some contractor and we have to supply material to them. We will charge for this.
Hi,
If you are charging for the Materials sent outside the Plant then follow proper sales process in SD Module. Create Contractors as Customers and then do following cycle in SAP;
(VA01) Sales Order > (VL01N) Outbound Delivery & PGI > (VF01) Billing Document
Here take help of SD Consultant also if required.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you Want to Return the Material which is in Excess / Damaged then Follow the Return PO Procedure
Create a PO with Item Return Indicator
Create Goods Receipt in MIGO for Return PO
If Material is Excisable, Create Excise Invoice for other Movements using J1IS & J1IV
Create a Credit Memo in MIRO