Hi experts,

how can i issue the material to outside the company.

The scenario is that we have some contractor and we have to supply material to them. We will charge for this.

Accepted Solutions (0)

Answers (1)

Answers (1)

pankaj_singh9
Active Contributor
0 Kudos

Hi,

If you are charging for the Materials sent outside the Plant then follow proper sales process in SD Module. Create Contractors as Customers and then do following cycle in SAP;

(VA01) Sales Order > (VL01N) Outbound Delivery & PGI > (VF01) Billing Document

Here take help of SD Consultant also if required.

Former Member
0 Kudos

i am creating a credit memo by follwing process

PO with tick mark on returns order(ME21N)-> MIGO with mvt type 161--> MIR7 with Credit memo

plzz tell that is this the right way for this

former_member192897
Active Contributor
0 Kudos

If you Want to Return the Material which is in Excess / Damaged then Follow the Return PO Procedure

Create a PO with Item Return Indicator

Create Goods Receipt in MIGO for Return PO

If Material is Excisable, Create Excise Invoice for other Movements using J1IS & J1IV

Create a Credit Memo in MIRO