Dear Experts Hello!
My question is that how do we get the daily progress report on day to day basis Which will show my work done for the day ,material consume for the day,labour/manpower utilized for the day and my cost /expense of the day.( comparison of my profitibility).
for that what r the data(input) i have to give in PS
waiting for ur valuable suggestion and reply.
rgds
sarfaraz khan.
Hi!
Check with Tcode CNE5 and in that go to Chose Field (Second Icon from left). select the required fields of report and execute. hope this can help you immensely if not fully.
If helpful, points please.
Regards,
Bekele
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Single Std. report is not available to cater this. U need to develop according to the requirement.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.