Dear all'

We are having mto scenario (non valuated) for which result analysis method 01 is used ,when i am running kka3 after partial billing system calculates cost of sales on the basis of percentage of completion (poc=actual revenue/planned revenue)planned costs.The planned costs calculated have huge variances as compared to actual costs i.e planned costs > actual costs,so my cost of sales is inflated as a result of which my wip is also inflatedi.e wip=actual costs-costs of sales.I want that method wherin system should calculate costs of sales as pocactual costs.Kindly provide any solution

Thanks and regards

vijay

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

In your RA key definition, in column, Valuation...

change valuation basis to J - Cumulative Actual Costs, Cumulative Actual Revenues

Former Member
0 Kudos

please put this question in CO form