09-19-2008 11:40 AM
Hello,
1. I would like to integrate the Workorders in the CICO Screen. Where it should be done? In Action box?
2. Following are the work orders need to be used.
- Field Verification
- Meter Removal
- Meter Installation
- Disconnection
- Reconnection
- Meter replacement
Can I create a single "Transaction" in the name work orders in "Technical" tab in Action box and use for all the work orders. Is it possible?
Regards, JACK
09-20-2008 8:18 AM
Hi,
I decided to integrate the work orders in Context menu of the objects as follows.
Meter removal, Meter replacement - In Context menu of Device.
Meter installation - In Context menu of Intallation.
Site Verifiacation - In Context menu of Premise
Disconnection / Reconnection order - From disconnection document.
Please give me your suggestions
JACK