Create account 45678 for 19.09.2008 as a cost element in controlling area G

Former Member
0 Kudos

Hi frds,

Create account 45678 for 19.09.2008 as a cost element in controlling area GVSK

Message no. KI280

Diagnosis

Account 45678 is a profit and loss account. You assigned it to an object in cost accounting (for example, a cost center, order, or project).

System Response

Account 45678 in the determined controlling area GVSK must exist as a cost element on the posting date 19.09.2008.

Procedure

Create account 45678 as a cost element and then repeat your posting.

Or, delete auxiliary account assignment to objects in cost accounting.

regards,

william

Accepted Solutions (1)

Accepted Solutions (1)

BijayKumarBarik
Active Contributor

Hi,

use t.code: KA01 and create Cost element 45678

T.Code: KA01

Enter u r controlling area GVSK

Then

account 45678

Valid from 19.09.2008 Valid to 31.12.9999

press enter

& Other details............

Save.

Regards,

Biju K

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Goto FS00, give G/L account and company code and enter.

Then click on Edit cost element,maintain mandatory data and take care of the date.

Regards,

Raviraj

Edited by: Raviraj on Sep 19, 2008 11:38 AM

former_member192897
Active Contributor
0 Kudos

> Create account 45678 for 19.09.2008 as a cost element in controlling area GVSK

> Message no. KI280

Please Create a Cost Element in KA01 Trxn code. Go to KA01 and Give Cost Element 45678 and Give Valid From field & Valid to Fields and Save.

Regards,

Ashok