Hi All,

We have two RS.

Net value limit 25000.01-9999999999.00 usd Higher level

Net value limit 0-25000.00 usd Lower level

My problem is that once RS trigger for 40000 usd Higher level and approved.Then after changes in PO Net value is only 10000 usd then system trigger Lower level RS that I don't know ?

In short once PO Approved higher level no need to trigger for any lower value RS.

How to retain the original Release strategy when the PO amount is reduced? It means when the amount is reduced, Release strategy should remain the same.

vIVEK

replied

Use release indicator as Changeable, no new determination of strategy against ur release strategy then system wont trigger a new release startegy even if the net value of PO is changed.