Dear all Hi,

I have a ROH material maintained as TON in MM. For calculating the qty required of this component i have maintained the formula in BOM as X factor multiplied with Y factor & divided by 1000 to get the output componenet qty in ton.

Though the system is calculating & displaying the qty in in ton with three decimals but the problem is that system is not giving the EXACT first three digits after decimal.

Example:

(16.08x0.22/1000x49 = 0.173 this should be the output in production order but it is displaying as 0.196

Kindly suggest a solution that system should display the actual first three didgits after decimal as it is.

Thanks in advance.

Accepted Solutions (0)

Answers (4)

Answers (4)

former_member406212
Participant
0 Kudos

Thanx all

dhaval_choksi3
Active Contributor
0 Kudos

Hi Shaiz,

How the problem is solved ?

Regards.

Dhaval

former_member406212
Participant
0 Kudos

Hi Dhaval

As such the standard SAP supports only 3 decimals in BOM & rounds off the 4th decimal to higher number if it equal to 5 or greater than 5.

regards,

Shaiz

dhaval_choksi3
Active Contributor
0 Kudos

Hi Shaiz,

What are this X factor , Y factor and 1000.And in which condition it change.

Regards,

Dhaval

former_member406212
Participant
0 Kudos

Hi Dhaval Choksi,

X factor is steel length, Y factor is steel diameter and 1000 is to convert in tons. Hope its clear now. Here only X will vary where as Y & 1000 remain costant.

Thanks in advance.

dhaval_choksi3
Active Contributor
0 Kudos

Hi Shaiz,

How the value of that X comes during order processing?Clarify with example.

Regards,

Dhaval

dhaval_choksi3
Active Contributor
0 Kudos

Hi Shaiz,

Check is there any Component scrap is maintain in BOM or Material Master.

I think there is 10 to 15 % component scrap is maintain either it is in BOM or in Material Master (MRP 4)

Regards,

Dhaval

former_member406212
Participant
0 Kudos

Hi Dhaval Choksi,

Thanks for reply.

There is NO component scrap is maintained either it is in BOM or in Material Master (MRP 4).

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

Check Decimal places and rouding of decimal place is maintain properly for the base unit of measure of that component in T.code CUNI.

Is there any Rounding value (value = 1) is maintain in MRP 1 data of that component

Regards,

R.Brahmankar

former_member406212
Participant
0 Kudos

Hi R Brahmankar,

Thanks for your reply. There is NO Rounding value (value = 1) is maintain in MRP 1 data of that component.