confirmation for order

Hi Experts,

please guide for the following,

SAP implementation is effective from 1st April-2008,

material consumed during this period is, directly posted to cost center by MM Consultant,

so,at the time of order confirmation,material are not in stock,or even it is in stock,issue of that material will double the cost,as it is already issued,

so now i can't do goods movement for the order,& hence completion,

suggest solution ,if there is any

thanks in advance

Former Member
Former Member replied

hi

without goods movement also we can confirm the order ,since you have already posted the cost in to the cost center.

just confirm the activities ,your labour cost will be settled to the cost center

regards

thyagarajan

0 View this answer in context