Hi sapgurus,

i am defining a release strategy for Purchase Requisition. but whenver in a strategy two release codes are incorporated suppose

Release group :MM

Release Codes: M1 and M2.

but in relese simulation tab showing

"M2 Release prerequisite missing"

and M2 code is not working in releasing pr.only M1 is worked.

Thanks in advance.

Regards,

Bipasha

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

GSWRT- For item level

GFWRT- for overall release

Former Member
0 Kudos

Thanks a lot Ravi.the Problem is solved.

Answers (11)

Answers (11)

Former Member
0 Kudos

What was the exact problem????

Former Member
0 Kudos

Then Its better delete these strtegies. Create 2 New strategies. 1 with value < (value of ur reqt) and relese code M1. 2 strategy with value > and release code M1and M2.

regards,

Raviraj

Former Member
0 Kudos

Yes Ravi I have done the strategy that u mentioned in 2 strategy but in ME54N, M2 and M1 should be shown .But only M2 is shown.

I took Field GSWRT for value determination. The field is right or not.

Former Member
0 Kudos

Hi,

It is only simulation. you wont get save button here.Once you double click on M1,if for M2 you get the message Release possible, then its working fine.

Now u go to ME51N create PR, check whether release strtegy is getting triggered. If yes Go to ME54N and release the requisition.

regards,

Raviraj

Former Member
0 Kudos

Hi ,

Ravi in ME54N only M2 is shown . M1 can not be shown.

Former Member
0 Kudos

Hi

PR Release Stgy

http://www.sap123.com/showthread.php?t=59

Regards

Ram

Former Member
0 Kudos

Hi,

In release simulation is it looks like this?

M1 Release possible

M2 Release prerequisite missing

If yes, double click on M1

then you get Release possible for M2.

Former Member
0 Kudos

Hi ravi after clicking M1 there is no save option so how the change will be made?

Former Member
0 Kudos

Hi,

Is your Release Prerequisite looks like this?

M1 M2

M1

M2 X

Release statuses look like this?

M1 M2

Blocked

X Blocked

X X RFQ/PO

If not modify it.

Edited by: Raviraj on Sep 19, 2008 9:45 AM

Former Member
0 Kudos

yes ravi that u said it is exactly the same .

Still it is not worked.

Former Member
0 Kudos

Hi,

Can u elaborate the steps what u r doing?

So that we can give the solution exactly..

regards,

Raviraj

Former Member
0 Kudos

Actually I want to create two release strategy

1. when total value in PR will be 1000.00 then one person can release PR.

2. when value is greater than 1000.00 then two persons will release.

For this i created a release group K1 with checkbox against 'OvRelPReq' is ticked.Then i have created M1 and M2 release codes are created.

Then I have given release indicator one for realesed and another for not released.

After that , create a relase strategy

where after M1 ,M2 can able to release the PR.in prerequisite button i ticked the checkbox near M2.

It will not work.

Plz give me a suggestion.

kunal_ingale
Active Contributor
0 Kudos

hi

check the configuration u have done as per following link

http://www.sap123.com/showthread.php?t=59

regards

kunal

Former Member
0 Kudos

u create 2 different release strategies with values > and < 1000 with release codes M1 and M1,M2 resepectively

former_member335885
Active Contributor
0 Kudos

Hi,

Have you done done release prerequistis settings.

I think you have configured in such a way that after M1 releases then only M2 should release.

Check the release statuses defined with the release indicators for these two release codes

Thanks & Regards,

Kiran

Former Member
0 Kudos

Hi,

Check the Release prerequisities in Release Strategy configuration.

Whether you have selected the checkbox both M1 & M2 release codes.

If both left side is selected then system will release first M1 then M2.

If you left any one this problem will rise.

Check & confirm

rgds

GSC

Former Member
0 Kudos

Hi,

if you set prerequisite,

M1 have to release it first and then M2 can release that.

Jason.

Former Member
0 Kudos

Hi,

Have u set prerequisites?

If yes until M1 is relesed M2 cannot release the PR.

Regards,

Raviraj

Former Member
0 Kudos

Yes i have done prerquisites .But Value of REL.OBJ is 1.

but still it can not be done.

Former Member
0 Kudos

Hi,

Just delete that release Strategy which you have created and then go back and create new release strategy for the same again.

with Release prerequisties to be selected for both M1 & M2 and process check

the Release statuses, then simulate the releases.

check & confirm

rgds

GSC