Hi Dear Friends
We have a issue where PS commitments does not match the PO receivings
The problem is
using T- code "S_ALR_87013558 " to show the commitment of project
we find that the commitments are not getting reduced after GR
The PO 's have GR more than the commitment quantities, still the commitment is not zero.
Looking for pointers to resolve this,
Regards
Run CJEN transaction for the Projects(s). This rebuilds the PS info database. This will correct in case there are mismatches.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
a
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Account assignment catagory is found from requirmnet class and requirment class from requirment type.
Check the requitment Class and requirment type config.
Regards.
Sukhveer.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.