Hello Experts,

I am getting problem in Using a parent product in BOM as component item (as child in same BOM).

It gives an ERROR :>> "Item is already defined at higher level in the product tree."

Help Required .....

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks

Former Member
0 Kudos

Hi Muhammad,

Using parent product in BOM as component item (as child in same BOM) will cause circlilar calculation. It is not possible.

What do you try to achive? Please explain.

Thanks,

Gordon

Former Member
0 Kudos

Thanks for your reply,

Actually we are in chemical manufacturing, in caustic soda liquid production caustic soda itself is used. That is why I would like to achieve this functionality. i.e. I wanted to add the Parent product that is Caustic Soda in BOM of Caustic Soda.

Help Required...

Thanks

Former Member
0 Kudos

If you have to include the similar item, you have to create two items for this purpose.

It is not logic to include both parent and child in the same BOM. If possible post the sample BOM of the both required parts here. I can look into it.

Thanks,

Gordon

former_member583013
Active Contributor
0 Kudos

Hello Riaz,

I really think you need a manufacturing Add-on for handling this.

Suda

Former Member
0 Kudos

Thanks Suda