on 09-18-2008 8:15 PM
Hello - can someone tell me if there a connection between th CVCs you have created using transaction /SAPAPO/MC62 and the /SAPAPO/MATKEY table? Should they be in sync?
/SAPAPO/MATKEY is purely based on the contents maintaiined in APO Product master(masterdata for SNP) whereas /SAPAPO/MC62 is used to generate CVCs(Masterdata of Demand PLanning) in Demand Planning. Both are completely different and need not be in sync
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In /SAPAPO/MC62 you have option to chech weather material/masterdata is already exist in APO or not (masterdata table /SAPAPO/MATKEY)and create CVC only if you have material defined in APO.
Check SCM master data check box in MC62 connects MATKEY table if you check it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.