cancel
Showing results for 
Search instead for 
Did you mean: 

Adjust Time Series

Former Member
0 Kudos

Hi

Our DP users, tick the box, adjust time series objects, while creating the CVCs and while leaving txn too.

But when they try to enter pl book, they get the error : Inconsistent state. No char combinations : No LC anchors.

But when i run the program TS_LCM_PLB_DELTA_SYNC, the problem goes off. But its really frustrating, to run this program everytime. Is system not supposed to adjust the time series, once that box is ticked ? Why we have to run this program everytime manually ?

Anyone faced this problme ? and How to get rid of this ?

Any help pls ?

thx

venkat

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

closing this thread.

Former Member
0 Kudos

Hi

I have this job running everynight. But this problem comes when users create CVC anytime, they wanted. It could be 3 or 4 times a day for New products. That time how can i plan to run the job ? But i clearly told them to click that box.

Even after checking that box, we have to adjust time series again manually.

Yes, i always run the PA cons check too.

thx

venkat

Former Member
0 Kudos

Hi Visu,

Check box on /SAPAPO/mc62 readjust timeseries object.

As Sai said best way to run this report at suitable time in background after master data team/planner create CVC.

Also suggest to run report for PA consistency check.

/SAPAPO/TSCONS - Consistency Check for Time Series Network

Manish

Former Member
0 Kudos

I can understand your issue..however, I recommend you to create a batch job and schedule it on daily basis to avoid this error