on 09-18-2008 7:14 PM
Hi All,
I have a custom Work flow in which I am trying to terminate a Decision Step via a terminating event.
Following Pre- requisites have been set:
1) In the Control task for the decision step I have assigned the terminating event.
2) Required linkages have been maintained via SWE3 transaction.
ISSUE: When the terminating event is raised then the Workitem for this steps gsts completed but workflow ends with an ERROR --> "No Successor for the terminating event defined".
Please let me know if any of you is familiar with the issue or have any inputs.
Thanks in advance..
Hi Sourabh,
There would be some binding problem going with Decision step while using Terminating event maintained at
the Task of the Decision step.
Rather go with FORK step with two parallel branch and 1 necessary branch. Specify the approval step in one
branch and wait for the release step event in another branch.
Hope this way would solve your issue.
Good luck
Narin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.