Alternative resources in production order - primary resource selected

Good evening,

I have a following problem, for which I have not found a solution:

we are using alternative modes in PPMs for reassigning orders to alternative resources and creating an order sequence for each resource in the Detailed Scheduling Planning Board (DSPB) in APO. However, when I convert a planned order to production order, this order is assigned to a primary resource again. Can I avoid this behaviour?

Thanks and best regards,

Jevgeni