Hi Experts,

I have a infopackage 000 version fullload. When we load version 000 based on the current period we need to go back 12 months and go forward 6 months. This should be done via a ABAP routine in the infopacakge. I have included the ABAP routine in the infopackage. Loaded data based on current period when i refresh the workbook it has displayed empty results. I check with R/3 system for 000 version data is available.

Regards

Prasad

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

First Check if the Routine in the IP is working good by using the Test tab in selection Screen.

If you find OK then Check if the selections used in the Wkbook are a subset of data loaded.

Also do some minor checks like request rolledup or not.

Thanks,

Prasad