Standard Costing

Dear SAP guru

I have run standard cost for XYZ material for 01/09/2008 - 30/09/2008 period with Altenate BOM - 1 on 01/09/2008

Today I have created Alternate BOM -2 and want to do costing

again for 18/09/2008 - 30/009/2008 period

But system not allow, error "Cost has released for the period"

Please suggest

Dharmesh Soni