on 09-18-2008 12:23 PM
Dear Friends
I have one issue :
If the final product is rejected from the customer end against sale order
the material will be returned to factory .
As a customer return will accept the material and by creating the return sale order
and later we will bring the stock to unrestricted by MM process .
Now how to carry out the rework of the same.
how to do that activity and rework order creation pls explain
total Rework order process in case of customer returns
Points wil be awared.
I know creation of rework order in case of line rejections.dont explain the process of line rejection rework.
rgds
Surya prakash
Hi,
1) You take the customer rejected materials into blocke stock (non valuated materials). MRP will not plan these parts.
2) You do the rework.
3) If found OK then transfer this to available stock (form blocked to un-restricted use). Now this will become valuated stock (relevent for costing and MRP).
Or,
Use inspection type 06 for customer return for that material.While doing return delivery you will find this material in quality stock.So create the rework order for material agianst notification.
Then book expenses in rework order.If compound found ok then send back this material to the customer while clearing from the quality to warehouse storage location.
Please refer this link also,
Regards
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.