Hi Everyone,

What is differecnce between MDVP collective ATP check and MD12 ATP.

I am getting different result for the same planned order.

could you plase tell me why this so.

Thanks

Siddhesh

replied

Siddesh,

Collective avaibility( MDVP) checks for all the orders that you have selected. Then based on each planned order basic start dates system allocates materials to different orders. So the order that you run ATP individually in MD12 may have a start date later than some orders in MDVP.

Hence the results can vary.Hope this helps. If yes please award points. Else please come back.

thanks,

Ram