on 09-18-2008 11:46 AM
Hi All
I have changed the lot size set up from EX(lot for lot) to WJ(8 weekly lot size).Immediately after the change i could see that the Rescedule in exception message and the dates proposed for the planned order and process order lieing within the planning time fence in MD04 disappeared.And after running MRP also the same condition persists.
Could anyone clarify why this happens.
Thanks in advance
Hi,
For rescheduling in please refer this useful link,
[Rescheduling date |http://www.sap-img.com/pp011.htm]
Hope it will help you.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks all
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.