Hi All
I need a solution for the following scenario:
In a continuous production scenario ,my BOM quantities vary according to the hourly results of the finished product.
End of the day actual consumptions are calculated and booked against the production.
Hoe do i create a bom in this kind of scenario , wherein the quantities of BOM vary every day?
Anil S
Hi,
Can you please check PP-PI functionality where you can use the options of Process instructions to calculate the new Process order Qts. depend on eariler closed process orders.
Require to test this part!!
Regards,
Shailendra