on 09-18-2008 11:15 AM
i am getting error "Not possible to determine any components" the BOM is not exploding while creating sub contract po.
hi,
BOm is created using CS01( tcode) and display in CS13...
check for material
and BOM ussage - 1(prod)
see for components and quantity.
Regards
Priyanka.P
Check and close your previous theads if answered....
Edited by: Priyanka Paltanwale on Sep 18, 2008 12:18 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to ME21N, Then enter the required data and in item category enter ' L ' which will enable 2 icons in the master tab in item details
there you have to enter the child materials for the parent materials then you will not get any error.
Thanks & regards,m
Kiran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Just want to add that you can manually put the components while creating the Po in ME21N in material tab in item detail
There you will found two push button BOM explosion which if you already creted the BOM with parent child relationship for the FG which serves as an Parent and components as child in Trax CS01
If BOM is not mantained then go to the components tab and Put tha material code and qty for the componenet materials.
Award if usefull
Regards
Sujoy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hope you have already Maintained BOM Properly for End Product.
Now Please Ensure the Following :
Purchasing Item Category must be "L" and production BOM must be maintained, if you want to explode BOM in PO.
Please check BOM valid period is effective from in Tcode CS03
Please check your PO date against the valid date of the BOM valid period.
Regards,
Ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check CS13 --BOM Display
Then check MM02 --For Semi finish material --MRP Views
Special procurement key 40-Subcontracting
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.