on 09-18-2008 10:18 AM
how is material planing run is carried out in MM. if so how the process is done. what are the steps and what type of planing run is available? please explain
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please follow below steps:
1. Maintain MRP plant parameters in the configuration (T.code: OPPQ)
2. make sure that you maintain all the required MRP fields (MRP type, MRP group, procurement type, Lot size key etc.) in the material master
3. Activate MRP and setup planning file entry (T.code: OMDU)
IN this case activate MRP run indicator for the plant
3. For the first time when you run MRP, use Processing key (NEUPL - Regenerative planning) in MD01 transaction.
Thanks,
Kiran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For all the planning the dates are predefined(defined by use) in the system...it may monthly, daily, periodic planning run...so on the given date the planning run will happen and for the req. qty the procurement will be hit...
types of planning:
Planning in total horizon
planning in opening horizon
planning in planning horizon
Regards
Priyanka.P
Edited by: Priyanka Paltanwale on Sep 18, 2008 12:14 PM
hi,
Check the link and follow tree path:
http://help.sap.com/erp2005_ehp_03/helpdata/EN/a5/e82be6a27311d3a82e0000e82a3c24/frameset.htm
Regards
Priyanka.P