hi frds,

while doing goods issue and intial stock posting. i am getting this message.how to clear this.kidly give your suggestions.

regards,

william

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

As per error you are getting it seems some might have changed the batch management level activation.

check this in customizing

SPRO->Logistic general->Batch management->Specify Batch Level and Activate Status Management->Batch level.

It seems earlier it was maintained at material or plant level some one might have changed it check the same.

Regards

Ravi shankar.

Former Member
0 Kudos

thank u .

i have activated batch level in material level by changing it from client level

Former Member
0 Kudos

t-code is omct