Hi

The scenario is, to manufacture material u201CAu201D, I need 0.2 qty of material u201CBu201D

I created a BOM for u201CAu201D (base qty is 1) with BOM component u201CBu201D, component qty as 0.2.

I created PIR for u201CAu201D for 5qty, I run MRP & I can see planned order created for u201CBu201D for 1 qty (0.2*5).

When I change the PIR qty of u201CAu201D to 6qty & I run MRP again, the planned order qty for u201CBu201D is changed to 2 qty, but it should be 1.2 qty

The planned order qty for B is not getting created in decimals. Pls advice what are the settings need to be done to achieve this.

Thanks

UK

replied

HI kartik,

Maintain Decimal place rounding = 2.

Regards,

Dhaval