on 09-18-2008 10:05 AM
Hi Gurus,
I have quick question regarding implementation of WM from IM. We have about 5 storage locations under one plant A and three storage location under another plant B in the current IM environment
we are planning to merge all the plants and storage location is it possible, how it is please explain?
Best Regards
Chandra
Hi
Yes you can manage N number of plants and its storage locations in one warehouse
In your example you think you may have like below given
Plant A, it is having five storage locations 0001, 0002, 0003, 0004, 0005.
And also you have Plant B; it is having three storage locations 0006, 0007, 0008
You can configure at Path: SPRO>Assignment>Logistics Execution-->Assign Warehouse number to plant/storage location
Here you can assign the Plant and storage locations to one warehouse, you may have ware house only one- 001
I,e
Plant Storage location Warehouse
Plant A 0001 001
Plant A 0002 001
Plant A 0003 001
Plant A 0004 001
Plant A 0005 001
Plant B 0006 001
Plant B 0007 001
Plant B 0008 001
This is the main interface between IM and WM
Regards
Madhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.