Hi

I am getting following error in controlling .

You have not defined a CO account assignment for an account that is relevant to cost accounting.

System Response

Account 511001 is defined as a cost element.

This means that you must always specify a CO account assignment.

Procedure

Enter one of the following CO account assignments

Order

Cost center / cost center/ activity type

Sales order item (for a project or cost relevant)

Project / WBS element

Cost object (Process manufacturing)

Network/ Network activities

Business process

Profitability segment

Real estate object

The posting row affected is 0000000001, account 511001.