cancel
Showing results for 
Search instead for 
Did you mean: 

date on project tiggered by sales order

Former Member
0 Kudos

Dear experts,

when project is triggered by sales order, my client requests the P/O date in the S/O be the start date of the project, and the req delivery date be the finish date of the project. they need the start and finish date be filled in automatically when the project is created.

i want to know if it is possible to do so?

i did some trials and found the project finish date is relevant to S/O req delivery date and the material master data.

thank you very much.

Best regards

Judy

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

you have two choices for this - either use assembly processing for this or substitution with exit

Former Member
0 Kudos

could you give me some detailed information on assembly and project dates?thanks

Answers (0)