What is rounding profile in CMIR?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member204513
Active Contributor
0 Kudos

Dear Krishnan,

Rounding Profile

Key that the system uses to adjust the order proposal quantity to deliverable units.

Procedure

In Customizing, enter a threshold value from which the system should round up to the next value per deliverable unit:

If the requirements value exceeds the first threshold value, the system always rounds up to the next multiple of the level found

If the requirements value falls below the first threshold value, the system copies the original requirements value.

Two other types of rounding exist:

Dynamic rounding profile:

These profiles are used to round up quantities to logistical units of measure (for example, layers). The contents of a logistical unit of measure does not have to be know when creating the rounding profile. It is determined by the master data from the material master.

Rounding profile with quantity to be added/subtracted

With these profiles, the given quantity is changed either by adding a percentage or subtracting a percentage.

Only static rounding profiles are taken into account in requirements planning. Neither dynamic rounding profiles not quantity addition/ subtraction are taken into account.

Examples

A material's base unit of measure is 1 unit; the purchase order is to be delivered in layers (1 layer corresponds to 5 units) or in pallets (1 pallet corresponds to 8 layers which contains 40 units).

You maintain the profile as follows:

From a requirements of 2 units, the system is to round up to 5; from a requirement of 32 units, the system is to round up to 40.

This results in the following order proposal quantities:

Requirement from 1 -> 1 requirement from 31 -> 30

Requirement from 2 -> 5 requirement from 32 -> 40

Requirement from 6 -> 10 requirement from 74 -> 80

Requirement from 7 -> 10

Dependencies

If no rounding profile has been entered, the system uses the rounding value entered in the material master record for the planning run.

I hope this will help you,

Regards,

Murali.

Former Member

Dear Krishnan,

Is it possible to create rounding profiles WITHOUT entering/connecting these to a plant???

kind rgrds

M. Kasar