sheduling error message no:ct604

Former Member
0 Kudos

hi

gurus.

while converting planned order to production order Iam getting following error i.e shduling parameters are not defined for production orders messge no:ct604.

please give solution how to solve it.

Thanking you.

mohan.d

Accepted Solutions (0)

Answers (2)

Answers (2)

rupesh_brahmankar3
Active Contributor

Hi,

Have u created new order type? OPJH & order type depenedent parameters at OPL8 for it?

For Order scheduling u have to define scheduling parameter at OPU3 for order type/plant combination.

Activate "schceduling" check box for selction Id at detailed scheduling section or any of one of scheduling level as as defiend.

And in Define production scheduling profile - OPKP, link your order type in the page below.

In material master work scheduling view, input production sch profile or prod scheduler.

Hope clear to you.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi,

May be you have not maintained Scheduling parameters for order type for that order.

go to OPU3 and maintain the same.

Sumeet