on 09-18-2008 6:56 AM
hi
gurus.
while converting planned order to production order Iam getting following error i.e shduling parameters are not defined for production orders messge no:ct604.
please give solution how to solve it.
Thanking you.
mohan.d
Hi,
Have u created new order type? OPJH & order type depenedent parameters at OPL8 for it?
For Order scheduling u have to define scheduling parameter at OPU3 for order type/plant combination.
Activate "schceduling" check box for selction Id at detailed scheduling section or any of one of scheduling level as as defiend.
And in Define production scheduling profile - OPKP, link your order type in the page below.
In material master work scheduling view, input production sch profile or prod scheduler.
Hope clear to you.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
May be you have not maintained Scheduling parameters for order type for that order.
go to OPU3 and maintain the same.
Sumeet
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.