Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Reson for creation of Planned & Production Order ?

Hi,

I m having 1 material in Project(PS) with req qty as 4 and Production order is there with delivered n released status for the same. but when i m running COOIS its showing two Production order for the same.

1. Wth 4 quantity with delivered status.

2. Wth 1 quantity in Committed.

I m looking for the reason behind creation of 2nd Planned n Production order wth 1 qty which is showing the same WBS element as 1st Production order. I hav checked that material in project also. It is used Once in Project order with Req qty as 4 n Withdrawal Qty as 4.

Pls guide me to chk the reason behind the creation on 2nd Planned n Production Order with qty 1.

Thanks.

Amit Jain.

Former Member

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question