Hi All,
please explain me whats the different between t.codes CJR2 and CJ40.
can we use CJ40(planned cost overall) for instead of CJR2(planned cost annual).
thanks & regards,
arun
Hi Arun,
CJR2 used to enter the planned values degregated into several cost elements, so you can get a better results when comparing plan/actual reports, where you can see deviations by cost element.
CJ40 used for just plan a total value, with no cost element specifications.
Regards,
Satish Muvva.