Batch - Production Date

Experts,

I need your help in order to solve one problem. The system is not filling the field MCH1-HSDAT (Production Date) ie. TR. CO15. Do i have to do something in SPRO or maybe use a user-exit?

Full points if helpful !!!

Best regards,

Mário.

replied

Hello

Please check below points,

1.The self life expiration date check is active for the Plant

2.The self life expiration date check is active for the Movement type ie 101.

3. Total shelf life & minimun shelf life period at material Master record.

With above settings will ask for the prodiction date while doing GR.

Regards

Pradeep Kumar