How can I display the description of Project Definition and the description of WBS element in CM01?
Thanks
Hi
In CM01, double click on the requirement line--- u will be in the details of the capacity screen... in the menu bar there is a tab "choose fields". from this choose the field WBS element and drag it to left...
A separate column will be displayed for each capacity requirement
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Yes it is not there in the std. screen selection. Only the description for order i.e. network can be selected.
I can think of two ways to cater this requirement-
1. Go for the development to add the new fields in the selection. You need to use module pool SAPMC65A for this.
2. There is a possible way out avoiding the development. We can make use of the user defined fields of activities. Since the user defined fields are available for selection... we can copy the description (upto 20 characters) and can display in the report.
Regards