Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Posting actual costs from cProjects to Internal Orders

Hi,

I am using cProjects 4.0 with integration using Internal Orders. When doing financial planning the planned costs are getting updated in the internal order, however, once a task is completed and confirmed... I would like the actual cost (based on the number of hrs/days confirmed) to post to the internal order. However, this is not happening and only the planned costs are updated.

Lets say for example, Project Manager (cost of $100/hour) role is assigned to Task A (work of 5 hours). This planned cost of $500 is updated in the internal order. When I complete the task and lets say enter confirmation of 5 hours work and change status to complete, I expect the internal order to be updated with $500 actual cost. However this is not happening. Is my understanding of the way the system should work correct?

Appreciate any help on this...

Thanks,

Lashan

Edited by: Lashan Wanigatunga on Sep 18, 2008 4:07 AM

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question