Dear PS Gurus
Pl tell me how to distribute my planned cost and planned revenue equally over planning period.I should able to see in reporting system its equal distribution period wise.
At present I am only able to see total planned cost in a period in which I have planned.
Best Regards
Adwait
Use Distribution Key 1 for equal distribution across the year. But you have to use annaul planning.
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
use distibuition key 2
CJ40
enter overall plan values for WBS
select WBS
click on Primary cost and then annual l overview button use distribution key 2
you can same for activity input for seconday cost planning
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use Annual Planning, instead of Overall Planning.(CJR2/CJ42). and use appropriate standard distribution key.
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.