on 09-17-2008 2:49 PM
hai pradeep,
It is possible to spilt the Order
Steps to split order :
1. In OPL8 Set the indicator cost collector
2. Default Rule -Periodic settlement(PP2)
3. CK11N do standard cost estimate
4. KKF6N Create cost collector
5. Create production order with op10,20,30,40
6. Go to op overview
7. Select the op from which you want to split (exop20)
8. Go to functions -
> Split order
9. Enter the qty ,if necessary a different order type for the child order
10.Execute
but i have the problem. when im trying to click SPLIT ORDER in function in production order . its in display mode.
what i have to do so??
note: i had done first two settings in opl8
Prakash,
Please note that Order split is only allowed for Production orders(PP module). If you are using PRocess orders ( PP-PI) order split is not possible. In ECC 6.0 you can plug in High tech solution & only then
Process orders can be split.
So incase You refer to process orders you have to use High tech inductry solution to get this functionality.
Hope this helps. If yes please award points. Else please come back.
Thanks,
Ram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Prakash
Goto Operation overview ->Select the operation from which you want to split the order->Function-> Split Order.
If not possible, Please check with order & operation status.
Please try and combeck
Regards
Pradeep Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Certain prerequisites must be met before you can perform an order split.
System Status
An order split is allowed with the following system status:
Header status: Partially released, released, partially confirmed
Operation status of the split operation and all successors: Created, released, partially confirmed
The order split is not allowed with the following status:
Header status: Created, delivered, finally confirmed, locked, technically complete, closed, deletion indicator set
Operation status of the split operation and all successors: Finally confirmed, dispatched, partially dispatched, capacity split, capacity requirement assigned, capacity requirement partially allocated
Operation status of the split operation: Deleted
Open Confirmations
Release the operation or Order and do the order spilt
Regards
Pradeep Kuamr