assign project to timesheet

monicabhosale
Active Participant
0 Kudos

how can i assign created project in timesheet plz help

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

you need to create a CATS data entry profile for WBS - I am assuming by projects you mean WBS and not networks

monicabhosale
Active Participant
0 Kudos

please send in detail if poss.

monicabhosale
Active Participant
0 Kudos

i am not aware with this HR module it would be helpfull

monicabhosale
Active Participant
0 Kudos

hi ...plz can you do one more help..now i am able 2 c created newwork and activity but in cat2 transaction its did not display project name in project filed...plz could you have help to resolve this prob...thanks in advance

nitin_patoliya
Active Contributor
0 Kudos

Hi

Please go through this link..

http://help.sap.com/saphelp_erp60_sp/helpdata/en/64/400b2b470211d189720000e8322d00/frameset.htm

As suggested by Virendra, with the help of HR person you can config the same.

regards

Nitin