Planning time fence

Dear Guru's,

Please let me know how planning time fence is calculated in Materials planning? I mean to say from where the planning time fence starts? This time we are maintaining in material master hence we could calculate the end date. If possible please describe with example.

Regards,

Yogesh

Edited by: Yogesh Raut on Sep 17, 2008 1:29 PM

Tags:
Former Member
replied

Dear,

Please note system will create 3 planned orders

Suppose that planning time fence is Ex. 25 days.From the date of MRP run, system will consider the planning time fence as 25 days onward.

Planning time fence is this time period in which system will not disturb the current plannng situation.Only manual changes are allowed.

Deciding no days in planning time fence , you have to take into consideration of normally your production cycle time.

Hope clear to you.