on 09-17-2008 11:41 AM
hi all
i have maintain all the required things for raw material.
in MD02 i have maintain value :
1
3
1
3
1
but when i see the MD04 i found only dep. requirement for raw materials, no purchase requisition.
can anybody focus on this?
i am confused.
thnks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Pl. check procurement type in MRP 3.It should be F.
Try the setting
2
3
1
1
1
subhash
Edited by: subhash kadam on Sep 23, 2008 7:29 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check your MRP type and External Procurement in MRP2 view?
Please check whether you have maintained the purchasing view for that raw material or not?
Please check if already there is stock of the raw material maintained in the system
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Do below checks,
- Check in MRP4 data of that Header materials.Planing for Dependent requirement should be planned or active
- MRP type of components it should be PD
- Check Plan order of that Header Material which is created during MRP - BOM is exploded or not. / Production version is selected or not.
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
check the MRP type for raw material in MRP1 view. It might be VB. So system will not create P.R.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.