Dear Gurus,

we run our COMAC run over all production order, but due the fact some controlling user is performing at the same time some settlement activity the job scheduled goes in DUMP and block all the chain of ATP scheduled for all Work Center, instead of provide an easy message log that advice the order processed bt the user has not taken into account?

there is something that is wrongly set up?

Regards.

Gianluca

replied

Do you think night also You open the order? Just see that schedule the AV check in such a way that you can do Co02 alter by fiving the message as i mentioned before

0 View this answer in context