production rescheduling problem

Hi PP Gurus,

I am seeking your help in below mentioned area.

I have created routing with following details -

Routing is having 3 operations

split is applicable in operation 1 and 2

overlapping is also applicable in operation 1 and 2

example -

Material code FERT

Bom Child component is HALB

Workcenter is available for 9 hrs only

Routing detail -

op no base qty processing time no of split send ahead qty

0010 2500 9.00 Hr 1 2500

0020 200 9.00 Hr 12 2400

0030 15000 9.00 Hr 0 0

We have created manual production oder with forward schduling. System derived schduled start and finish date.

Problem - If press reschduling button again there system is changing basic dates and schdule dates again and again. It happens till the availability of calender dates / years.

Please help me to come out of this problem.

Regards,

Abhay