GR on future date

Former Member
0 Kudos

Hi experts,

I have an issue regarding GR in MIGO.

Actually when doing GR in MIGO it accepts the future delivery date materials.

for eg. - In schedule agreement the delivery date is set for October but when doing MIGO for the same on todays date, the system accepts and shows the GR quantity on Octobers date in the schedule agreement.

So is there any setting in the schedule agreement, by which we can deactivate GR being done on future delivery date.

Regards,

Robin

Accepted Solutions (1)

Accepted Solutions (1)

dhrubacharan_behera
Active Contributor
0 Kudos

Hi,

In T Code OMCQ make the Message No.M7254 as Error .This will prevent doing GR before the Delivery Date .

Dhruba

Answers (1)

Answers (1)

former_member581212
Active Contributor
0 Kudos

this date is maintained in the MMR...

As Planned delievery date....

Pls check...

No its not possible...

But you can settle down GR...

Regards

Priyanka.P