on 09-17-2008 11:16 AM
Hi Experts
While doing CJ48 Payment Planning for WBS element group, I am getting following error
Group 0801 cannot be used
Diagnosis
Group 0801 has not been created in controlling area 0801 for the characteristic used, neither does it exist as a node within the group.
System Response
The SAP System rejects the row/column structure for group 0801.
Procedure
1. Create group 0801 with the group maintenance transaction.
2. Or, correct the name of the group in planning layout SAPPSCM1 or in the initial screen for planning.
I have checked everything and is correct.
Please help me out
Thanks,
Pravin
Hi,
Check if you have created WBS group correctly ( T Code KJH2). If not then create it using CJSG.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.