Hi all,

we r using PS for shutdown projects...

Can anybody give inputs on what all config is required in PS for assigning PM orders to WBS..?

Regards

pushpa

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

No specific config is reqd.

In IW32 on additional tab you can assign either:

1. WBS: this will serve for cost purpose

2. Network Activity: this will serve for scheduling purpose

Regards

virendra_pal
Active Contributor
0 Kudos

you might want to consider OPSV to append plan costs from maintenance orders

Former Member
0 Kudos

Hi Virendar,

requirement is to reflect the MO planned cost in Commitments so wht r the rquired setting for tht ?

Regards

pushpa

virendra_pal
Active Contributor
0 Kudos

Look at mails above

From Shrikant - Assign order to WBS

Set order type append flag in OPSV to get plan costs

Former Member
0 Kudos

In OPSV transaction if there is a check in check box under column 'assign funds in plan' and 'addit.', against order category 30, commitment value check should work. There is no other setting required for this.