we r using PS for shutdown projects...
Can anybody give inputs on what all config is required in PS for assigning PM orders to WBS..?
Regards
pushpa
Hi,
No specific config is reqd.
In IW32 on additional tab you can assign either:
1. WBS: this will serve for cost purpose
2. Network Activity: this will serve for scheduling purpose