Hi,
For MRP type VB, system will plan for that level only, system will not plan one level below.
For one semi finished material, system will create P.O for that material. It will not create P.O for raw material.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
MDBT transaction is used to for background MRP Run Create a Variant with your requirements from there.
In OM0E you need to create scope of planning, then you have to create the MD01 variant with is data.
This variant has to get scheduled in MDBT. If you want immediately, or periodically you can decide here.
Click the below link for more details on how to proceed further.
http://www.sap-img.com/pp019.htm
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.