Hi ALL,

I am trying the Subcontracting Process,

Transfer 11kg RAW,Received 10kg FINISH,1kg SCRAP generated.

I Reconcile 11kg RAW(at that 10kg Finish also get reconcile) & enter scrap return by 542 mov type.

Want to know is it reqd to reconcile the scrap wrt challan.

Thanks

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

You can give (-)minus qty for scrap while creating the S/C Pur.Order.

Former Member
0 Kudos

ok

Former Member
0 Kudos

Dear,

Yes,U have to reconcille the challan for the scrap qty

regards,

SNB

Former Member
0 Kudos

Dear,

In J1IFQ, System shows me 3 line items for

101 mov-Finish

543- Raw

545-Scrap,

But while reconcile system shows message Scrap is not fully assigne short by 1kg.

Plz suggest is it reqd to reconcile scrap. If yes then how to do it.