Automatic Scedule line in MD03

Dear Team

System is creating PR instead of crating Schedule Line after running MD03 for Current Month,Plz suggest.

I did Following Setting

1.MM01 with MRP Type PD,MRP Controller,MRP Group, Lot size EX,Prcument Type-F, Planned Del Date-1,Scehduling Margin Key-000,strtegy Group-10,TRLT-1

2.ME31L(Creation of Scheduling Agreement)

3.ME01 chick box is tick for Fix, and MRP-2 with SC number

4MD61- For month 9-1200qty,for month10-500 qty for month11-900 qty

5.MD03-System is creating PR for 1200 qty and for 500 and 900 qty it is creating scheduling Lines...