Hi experts,
I want to close the Projects. While closing the project i am getting an error that "Balance of the network (N/W no & Activity No)* is not Zero".
Related to project it is giving an N/w No & Activity Number.
Can anybody please solve this issue.
Can anybody tell what are the steps want to be carried out before closing the project.What are things i want to check.
Regards
Raman T S
Dear Raman,
Before closing the project u have to insure that all commitment should be zero.
so u check that activity it must carried some commitment so either make it in actual or delete it.
Regards,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
U need to carry out settlement before closing.U can carry out settlement thru transaction CJ88
Initially create settlement rule there are lots of posts on SDN rgding settleent will help u to carry the process.
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.