on 09-17-2008 5:19 AM
Hi,
Is there any config setting that enables us to define pricing conditions/changes based on the schedule line level?
Thanks in advance
Done through Customiztion
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kase,
You mean to say maintaining the condition records (condition type value)based on the schedule line category.
Regards,
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The issue is, im getting an incompletion log when i enter a rejection reason for a schedule line. (saying Net value is 0)
When i enter a rejection reason fr a line item, im able to save with out a problem.
When i enter a line item with 2 schedule lines, and reject one schedule line only, it gets saved without a problem.
But the log comes when we reject a schedule line where the line item has only that schedule line.
So, i was wondering if there's a config setting for conditions based on schedule line levels?
And also, when we reject a schedule line, and go to Item>Conditions, does all the values (including Net) be shown as 0? Or should the values be shown, marked as Inactive?
Thanks in advance
Can you explain your scenario a lil better please.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.